Bathrooms fail in slow motion. A poorly sealed shower does not flood the room on day one; it quietly sends water into the floor structure for a year and then shows up as a soft patch, a musty smell or a stain on the ceiling below. By then the repair is several times the cost of doing the sequence properly.

The sequence below is the one that experienced bathroom fitters follow. It is not glamorous, but it is the difference between a room that looks finished and a room that stays sound.

The short version

  • Design and price the room before demolition, including the position of every waste pipe.
  • Strip out, inspect the structure, then complete first-fix plumbing and electrical work.
  • Waterproof the wet areas before any tile is laid. This is not optional.
  • Tile walls and floor, then fit sanitaryware, then seal and commission.
  • Test everything under pressure and let the room dry fully before final sealing.

Before demolition: design the services

The layout of a bathroom is largely the layout of its waste pipes. A toilet needs a fall to the stack, a shower needs a trap and a fall, and a bath needs enough space beneath the floor or behind the wall for the waste. Decide these positions before you buy a single tile.

Measure the room properly, including door swing, window position and the depth of any boxing. Check where the soil stack runs and whether a new position can connect to it with an adequate fall. If you are moving a toilet across the room, the floor may need to be raised or the ceiling below lowered. That decision belongs in the design, not in the middle of the build.

This is also the moment to plan ventilation. An extractor fan should be sized for the room volume and ducted to the outside with as short and straight a run as possible. A fan that recirculates into the loft is a decoration, not ventilation.

Strip-out and inspection

Remove the old suite, tiles and floor covering, protecting the route out of the house. Once the room is open, inspect the substrate. In older houses you may find rotten joists, failed screed, old lead pipework or evidence of long-term leakage. Deal with these before anything new goes in.

Check the walls for square and plumb. A wall that is 20 mm out over a metre will make large-format tiles look uneven and a shower screen sit badly. Correcting it with new boarding or skim is much cheaper now than after tiling.

A tiler applying waterproof membrane to a shower wall with a roller
A tiler applying waterproof membrane to a shower wall with a roller.

First fix: plumbing and electrical

First fix means everything that goes inside the walls and floor: supply pipes, waste pipes, shower valve bodies, electrical cables, fan ducting and any underfloor heating. Photograph all of it with a tape measure in frame before it is covered. Future you will be grateful.

Pressure-test the pipework before closing the walls. A simple air or water test at the specified pressure will reveal a joint that was not tightened. It is far easier to fix now than through a finished tile.

Electrical work in a bathroom is regulated in most countries because of the shock risk. Respect the zones around baths and showers, use the correct IP ratings and have the work certified. A shaver socket is not a substitute for a properly located general socket.

Falls and drainage

Every wet area needs a fall to the drain. In a shower, the fall should be continuous and the trap accessible for cleaning. A linear drain can look minimal, but it needs a precise screed and a trap that can be reached. A standard round trap is less elegant and much easier to maintain.

Test the waste runs with water before the floor is closed. Pour several litres down each drain and watch for leaks and slow flow. A trap that gurgles or drains slowly will only get worse once the room is in use.

A plumber fitting a wall-mounted shower valve before tiling
A plumber fitting a wall-mounted shower valve before tiling.

Waterproofing

Waterproofing, or tanking, is the step that separates a professional bathroom from a hopeful one. In a shower area, apply a liquid membrane or a sheet membrane to the walls and floor, including the junctions, corners and pipe penetrations. Follow the manufacturer's coverage rate and curing time exactly.

Build in a water test if the system allows it. Fill the shower tray area with water and leave it for 24 hours, then check the room below. This is standard practice in many commercial projects and far less common in homes, which is a shame because it catches most failures before they become expensive.

Do not rely on tile adhesive or grout as waterproofing. Both are water-resistant at best, and both crack. The membrane does the work; the tile is the visible layer.

Water always finds the path you did not detail. Seal the corners, the pipe entries and the door threshold, and the rest of the room can be ordinary.

Tiling and finishing

Tile the walls before the floor where possible, so the floor tile can die neatly into the wall. Use a levelling system on large-format tiles and check for lippage with a straight edge. Plan the layout so cuts fall in inconspicuous places and the grout lines align with the room's geometry.

Allow the adhesive and grout to cure fully before fitting sanitaryware. Then install the toilet, basin, bath and shower screen, connecting the wastes and supplies. Use flexible connectors only where access exists for future maintenance, and support wall-hung fixtures on a proper frame rather than plasterboard alone.

A finished bathroom with large format tiles, a walk-in shower and a floating vanity
A finished bathroom with large format tiles, a walk-in shower and a floating vanity.

Sealing and commissioning

Final sealing is a small job with a large consequence. Use a sanitary-grade silicone, not a general-purpose sealant, and apply it to a clean, dry surface. Tool the bead neatly and leave it undisturbed until cured. Silicone will not adhere to dust, soap residue or damp substrate.

Commission the room by running every outlet, checking the shower temperature and flow, testing the fan and confirming that every drain empties without gurgling. Look for leaks under the basin and around the bath. Run the shower for ten minutes and check the room below.

Close-up of a neat silicone seal along the base of a shower screen
Close-up of a neat silicone seal along the base of a shower screen.

The details that age well

Choose a floor tile with enough slip resistance for a wet room, and seal natural stone before installation. Provide accessible isolation valves for every supply so a future repair does not require demolition. Leave spare tiles and a note of the grout and sealant products in a cupboard.

A bathroom does not need to be large to feel generous. Good light, a clear layout, a proper mirror and a place to put a towel matter more than a freestanding bath. Get the sequence right, and the room will look good on the day it is finished and still be sound a decade later.